Quiz answers
- The correct answer is C.
Story points are used to indicate relative size and complexity. They do not denote time units. It is impossible to know whether an item is feasible to be completed within a Sprint, based on its story points, unless we know the estimation scale and baseline.
- The correct answer is A, C, D.
Having fixed dates in the Products roadmap goes against Agile and Scrum principles of constant inspection and adaptation versus following a set plan.
- The correct answer is C.
Estimating methods such as Planning Poker rely on developers reaching a consensus by giving individual estimates and then discussing the motivations behind the estimates until an agreement is made on a single estimate value.
- The correct answer is C.
Velocity is subjective to a specific team and product. It’s not a comparative measurement.
- The correct answer is B.
Velocity is used for charting and forecasting in the context of burn-up/down charts. Burn-down charts help...