- The correct answer is A, B, and C.
Creating tasks for delivering Backlog items occurs after the items have been selected for the Sprint Backlog.
- The correct answer is D.
The PO decides how the Product Backlog items are ordered. This can be by value, cost, risk, or other criteria.
- The correct answer is B.
The Sprint should aim to create a valuable, working product Increment. No Sprint is special.
- The correct answer is C.
The only reason to cancel the Sprint is when the Sprint Goal becomes redundant. This should be an exceedingly rare occasion.
- The correct answer is C.
If a defect is discovered on a “Done” item during the Sprint, then the item’s description, acceptance criteria, or the Definition of Done need revising. The item should be moved to the