Quiz answers
- The correct answer is D.
Stakeholders’ expectations should have already been addressed when defining the Sprint Goal (A). Sprint Backlog items should not need further refinement (B). Scrum Teams should not worry about work being taken over by other teams (C), but they should try to have as few dependencies between them as possible (D).
- The correct answer is B.
There is no such thing as a product integration phase (A). Unintegrated Increments have little value so should not be delivered (D). What should be delivered is the sum of all Increments (B), regardless of cross-team dependencies (C).
- The correct answer is D.
Although Ken Schwaber and others suggest a daily, 15-minute Scrum of Scrums, this is not always practical or fruitful. The organization should decide on the frequency and duration based on the number, size, and location of the Scrum Teams.
- The correct answers are B, F, and G.
The Developers do not re-order the Product Backlog; this is the...