Mock assessment answers
- The correct answer: B
A Sprint could be canceled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.
- The correct answer: D
A new Sprint starts immediately after the conclusion of the previous Sprint.
- The correct answer: C
The Developers are responsible for conducting the Daily Scrum. The Scrum Master teaches the Developers to keep the Daily Scrum within the 15-minute time-box. The Scrum Master also ensures that only Developers participate in the Daily Scrum.
- The correct answer: A
The Product Owner is accountable for Product Backlog management. The Product Backlog is an emergent, ordered list of what is needed to improve the product. The order of the backlog is determined by the Product Owner and may be done based on business value, priority risk, or any other method the Product Owner deems appropriate. The Scrum Master may advise the Product Owner on ways of ordering the Product Backlog.
- The correct...