Quiz answers
- The correct answer is C.
Although a Scrum Master can stop a Scrum Event if it becomes unproductive or toxic, an intense argument is not usually a reason to cancel the event altogether (A and B). Instead, a chance for cooler heads must be given and the team should be reminded of the Scrum Values and how such behavior violates them (C). The values of openness and courage are certainly not reflected in heated arguments (D).
- The correct answers are A and C.
Scrum Events are timeboxed to ensure effective communication and focus. Time management and presentation techniques can help maintain the event’s timebox while ensuring information is disseminated productively.
- The correct answers are B and C.
Partially Done items (A) should never be accepted. An item either meets the Definition of Done or it doesn’t. Sprints are never paused (D); they are either completed or canceled.
- The correct answers are C and D.
The Developers’ self-organization means...