Quiz answers
- The correct answer is C
The Sprint Backlog should contain enough items to get the Sprint started but items may be added or removed during the Sprint by the Developers.
- The correct answer is A
Time-boxed events are events that have a maximum duration.
- The correct answer is C
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.
- The correct answer is C
The Daily Scrum serves to inspect work done since the last Daily Scrum and plan work to be done in the next 24 hours.
- The correct answer is E
Th Sprint Planning duration is four hours for a monthly Sprint. For shorter Sprints, it is usually shorter.
- The correct answer is B
To ensure continuous improvement, the Sprint Backlog should include at least one high-priority process improvement identified in the previous Sprint. The Product Backlog should only contain product-specific items.
- The correct answer is B
The definition of...