Chapter 9, Handling Overallocations
Discussion points
Here are some key talking point questions that a trainer for Chapter 9, Handling Overallocations, could discuss with the participants:
- Question: What is resource overallocation, and why is it important to address it in a project?
Answer: Resource overallocation occurs when a resource is assigned more work than it can handle within a given time frame. It is important to address overallocation to prevent burnout, ensure timely project completion, and maintain team productivity.
- Question: How can you detect overallocations in Microsoft Project?
Answer: Overallocations can be detected using the Resource Sheet and Resource Usage views. These views help identify resources that are assigned more work than they can handle.
- Question: What is resource leveling, and how does it help in managing overallocations?
Answer: Resource leveling is the process of adjusting the start and finish dates of tasks to balance the workload...