Assessment exam answers (Chapter 5)
Question 1
You and your team are meeting to discuss the customer's feedback on the deliverable you created in this iteration. What part of the Agile life cycle are you experiencing?
- Review
- Retrospective
- Sprint planning
- Daily standup meeting
The review is an informal meeting with the customer and other stakeholders to review the work that's been done in the Sprint/iteration. The customer will demo, test, ask questions, and add new items that they find valuable.
Question 2
One of the team members is describing the work they did yesterday and their plans for today. What is the best time to discuss those areas of project work?
- Review
- Sprint planning
- Daily standup meeting
- Retrospective
The daily standup meeting allows the development team to discuss work in progress, work to be done, and any impediments to their progress. Typically, those meetings are 15 minutes long and informational...