Task constraints
In project management, task constraints help ensure that tasks start or finish exactly when needed, whether due to tight deadlines or limited resources. The table that follows will explain the various types of constraints, from flexible to strict or inflexible, and explain how to use them effectively to keep your project on track, especially when surprises appear:
Constraint name |
Type |
Explanation |
As Soon As Possible (ASAP) |
Flexible* |
By default, when you are scheduling from the start date of the project, Project plans a task to happen at the earliest possible time. |
As Late As Possible (ALAP) |
Flexible* |
By default, when you are scheduling from the finish date, Project assigns a task to happen at the latest possible... |