Chapter 6, Identifying and Managing the Critical Path
Discussion points
Here are some key talking points and questions that a trainer for Chapter 6, Identifying and Managing the Critical Path, could discuss with the participants:
- Question: What is the critical path in a project?
Answer: The critical path is the longest sequence of tasks that must be completed on time for the project to finish by its due date. It determines the shortest possible duration to complete the project.
- Question: Why is it important to identify the critical path in a project?
Answer: Identifying the critical path helps in understanding which tasks are crucial for the project’s timely completion. It allows project managers to focus on these tasks and ensure they are completed on time to avoid delays.
- Question: How can Microsoft Project help in identifying the critical path?
Answer: Microsoft Project automatically calculates and highlights the critical path once all tasks, durations, and...